Social Housing Implementation Plan - WA

Schedule A

National Partnership Agreement on Social Housing

The Commonwealth has approved the following projects to be funded in Western Australia under the National Partnership Agreement on Social Housing.

Project Details
Project Number Location Number of new dwellings
2008-09
1 Ellenbrook 7
2 North Beach 3
3 Tuart Hill 5
4 Beaconsfield 10
5 Beeliar 9
6 Albany 2
7 North Metropolitan 9
8 South West (Bunbury) 32
  Total 2008-09 77
2009-10
1 Karratha 7
2 Innaloo 5
3 Wellard 2
4 Kewdale 4
5 Queens Park 6
6 Albany 4
7 Northam 4
8 Kalgoorlie 2
9 Ellenbrook 3
10 Walnut Grove 4
11 Broome 1
12 Geraldton 4
13 Ellenbrook 10
14 Ellenbrook 3
15 Northam 1
16 Albany 12
17 Esperance 4
18 Bunbury 4
19 Bunbury 4
20 Geraldton 9
  Total 2009-10 93
  Grand Total 2008-09 & 2009-10 170
National Partnership Agreement on Social Housing funding and reporting arrangements for Western Australia in 2008-2009 and 2009-2010
Financial Year Reports Due Payment Date Payment Amount
Comprehensive / Status Report
2008-09   7/06/2009 $20,244,000
2009-10 31/07/2009 7/09/2009 $5,061,000
31/10/2009 7/12/2009 $5,061,000
31/01/2010 7/03/2010 $5,061,000
30/04/2010 7/06/2010 $5,061,000
  Total Funding 2008/09 $20,244,000
  Total Funding 2009/10 $20,244,000
Total National Partnership Agreement on Social Housing funding $40,488,000

This schedule may be varied through an exchange of letters between Ministers. Last approved on 14 July 2010.

 